Design & Planning
October 20, 2021 - we've been working closely with Slaggie Architects and the City of Lee's Summit to design an incredible building as the first ever ground-up build for a K1 Speed location.
Owned and operated by Midwest Karting LLC, an independent K1 Speed franchise. We are proud to offer the following family-friendly entertainment activities:
October 20, 2021 - we've been working closely with Slaggie Architects and the City of Lee's Summit to design an incredible building as the first ever ground-up build for a K1 Speed location.
September 14, 2022 - celebrating the start of construction as we broke ground and the Centric team began shaping the pad site for the 46,000 square foot building and parking lot.
December 5, 2022 - an exciting day as the crane began to raise the tilt-up wall panels into place. Giving us our first look at what will become the exterior shell of the building.
January 17, 2023 - it's incredible to see the progress in just over a month, as the exterior skeleton of the building is in place. Now the roof can go on and the front elevation can begin framing.
February 19, 2023 - now that the walls are up, structural steel is in place, and the roof is nearly done... we can see the shape of the building's front facade come together.
March 7, 2023 - you can really see the design becoming a reality. And what you don't see is all the work going on inside and up on the roof, with plumbing and electrical well underway.
April 27, 2023 - the exterior paint scheme is nearing completion. The red wall on the Southeast corner that faces Interstate 470 is really going to pop!
April 27, 2023 - the excitement continues inside with the framing of walls, painting of the track area, and rough-in of mechanical, electrical, and plumbing.